Giga Texas Optimus factory construction update with 2 short video clips, one 360 at medium-altitude & a closer, lower flight showing tight views of the main steel structure!
Ground work started in late March, with 1st steel on May 27. By 1 October, the frame was nearly at the
Ground work started in late March, with 1st steel on May 27. By 1 October, the frame was nearly at the